Major changes in building regulations in Bihar, paving the way for the construction of 100-storey buildings

By Awaz E Bihar4 min read

Building Bye Laws 2026 implemented; provision for automatic approval if plans are not approved within 30 days; FAR increased to 3, additional concession of up to 15 percent for those building green buildings

Patna: (ABN) The state government has made major changes in construction laws for home builders, builders, and those associated with the real estate sector in Bihar. After cabinet approval, the 'Bihar Building Bye Laws 2026' have introduced a new system, replacing the building regulations in force since 2014. The aim is to simplify the process of obtaining construction permits, increase construction capacity on small plots, promote investment, and provide citizens with better residential facilities at lower costs. Minister for Urban Development and Housing Nitish Mishra said in Patna on November 17 that under the old laws, it took a considerable amount of time to approve building plans and obtain No Objection Certificates (NOCs) from various departments. The new regulations have reduced these complexities.

The government is trying to make life easier for common people along with Ease of Doing Business. According to him, before formulating the new policy, a special group of ministers consulted with stakeholders and experts so that investment and employment opportunities could be increased.

According to information released by the state cabinet, a concession has also been given in the mandatory requirement of getting plans approved for buildings up to three storeys. However, the application of this facility will be in accordance with the prescribed conditions, building use, plot, and other safety regulations. It should not be considered a complete exemption for all types of construction.

Under the new regulations, the validity of approved construction plans will be five years. There is a provision for a further five-year extension along with the prescribed fee. A facility to obtain a permit under prescribed conditions and fees has also been kept for already constructed buildings. The process of fire safety approval has also been integrated with the construction permit system so that citizens do not have to go through separate bureaucratic procedures. Minister Nitish Mishra said that the government's aim is to promote the construction sector while providing better facilities to common citizens at lower costs. These changes are expected to increase investment in real estate, construction activities, and employment opportunities. However, the real success of the new laws will depend on whether basic facilities such as roads, water, sewage, electricity, parking, and fire brigade are also improved in proportion to high-rise buildings.

30-day period for plan approval: Previously, there was a delay in the inspection by civic bodies and bureaucratic procedures for plan approval. Now, the relevant authorized body will have to make a decision within 30 days. If no decision is made within the prescribed period, the plan will be deemed automatically approved under legal provisions. A self-declaration system has been arranged for low-risk buildings up to 10 meters, and approval through a list of technical experts for buildings from 10 to 24 meters. Approval from the relevant civic body will be necessary for buildings taller than 24 meters.

General height limit for buildings removed: There were various restrictions on the height of buildings under the old system. The general maximum height limit has been removed in the new regulations. This has made it possible to construct 100-storey buildings. However, this permission will not be uniform everywhere. Full compliance with airports, air space limits, historical buildings, fire safety, and other legal restrictions will be necessary.

Four sides of the building have setback spaces, with one side having an empty space: Previously, there was a rule to leave a fixed distance of empty space around the building, which reduced the usable area for construction on smaller plots. The new regulations allow a fixed setback on one side, so that the fire brigade and emergency vehicles can access the rear of the building, and the remaining land can be used more efficiently. For this, a minimum 3.7‑meter‑wide access road standard is also essential.

FAF and additional construction facility: Previously, the floor area ratio (FAF) was largely determined by the road width and the nature of the area. The new system sets a basic FAF of 3 and allows the purchase of additional premium FAF in exchange for a fixed fee. This will provide opportunities to increase construction area and enable better land use.

Changes in parking regulations: Previously, there were various standards for parking requirements and calculations. Now, a standard of 15 square meters per car is set. In residential buildings, one car parking is provided per residential unit; in commercial, educational, and institutional buildings, one car per 100 square meters of built area; and in industrial and warehouse buildings, one car per 300 square meters. The mandatory parking area will not be counted in the FAF.

Encouragement of green building and eco‑friendly construction: The new rules grant special incentives to environmentally friendly buildings. Buildings with a three‑star certificate receive an additional 5% FAF, four‑star buildings receive 10%, and five‑star buildings receive 15% additional FAF. This aims to promote energy savings and environmental protection.